Services

“Turnkey” photovoltaic system on the roof for industrial and residential use

The construction of a photovoltaic system, due to its complexity, requires a lot of experience and a specialized know-how in order to cope with any problems encountered during the development and implementation phase.

Seasolar Group owns this experience and puts it at your disposal.

For our customers we design and build photovoltaic systems of any capacity.

Our work begins with the first inspection and ends with the delivery of the “turnkey” photovoltaic system.

The “turnkey” service includes:

  1. Preliminary inspection on the installation site
  2. Technical and financial feasibility report
  3. Preliminary design
  4. Instructing and forwarding the Declaration of commencement of work to the relevant Authorities (if required by local regulations in force)
  5. Connection request for the photovoltaic system to the National Transmission Grid (to be forwarded to the local Grid Distributor)
  6. Final design according to local regulations in force
  7. Works management and coordination
  8. Supply and installation of photovoltaic modules, mounting systems, inverters, electric field panels, electrical switchboards, general electrical panel, switchboard interface to the National Transmission Grid
  9. Cold Testing and verification of the photovoltaic system
  10. Instructing and forwarding the Declaration of completion of work to the relevant Authorities (if required by local regulations in force)
  11. Instruction and forwarding the request for activation of the connection for the photovoltaic system to the National Transmission Grid (to be forwarded to the local Grid distributor)
  12. Instructing and forwarding the Census for photovoltaic plants to the National Transmission Grid’s owner (if required by local regulations in force)
  13. Instructing and forwarding the request to Customs Agency (if required by local regulations in force)
  14. Instructing and forwarding the request for the granting of the incentive rate (depending on local regulations in force)
  15. Activation of the photovoltaic system’s connection to the National Transmission Grid
  16. Hot Testing and verification of the photovoltaic system
  17. Delivery to the Customer of the “turnkey” photovoltaic system.